The interior decoration work comes to the final stage at the main terminal building of Beijing Daxing International Airport, with the “Ruyi Xiangyun”design officially taking shape.

The entire decoration work is expected to be completed by the end of April, said Li Jianhua, the project manager for the main terminal building from Beijing Urban Construction Group.

Li said, the project will enter the stage of adjustment, inspection, commissioning and acceptance check in May to ensure a smooth project completion by the end of June.

Beijing Daxing International Airport’s terminal is the first in the world that adopted a two-story design for departures and arrivals each with a high-speed railway running through below.

It will open to traffic in September 2019.